Im still trying to figure out whos in charge of the Kalorama Park project, - whos dealing with
quality control, and how much the project will cost. Based on an e-mail exchange with Jim Graham,
I contacted Neil Stanley from the Department of Parks and Recreation (DPR). In response, Jackie
Stanley said that I would get a response by the end of last week - still waiting - see exchange
below.
Both Jackie and Neil Stanley along with Drew Becher all from DPR have been added to the Mintwood
List.
If neighbors on this list, would note progress and problems it would definitely help our friends
at the Department of Parks and Recreation better monitor the Kalorama Park reconstruction.
Thanks, Eddie
--------------------------------------------------------------------------
Eddie Becker <eddie_becker at yahoo.com> wrote:
> Date: Sat, 20 Nov 2004 19:19:20 -0800 (PST)
> From: Eddie Becker <eddie_becker at yahoo.com>
> Subject: More details on KALORAMA PARK project
> To: Neil.Stanley at dc.gov
> CC: jim at grahamwone.com
>
> Dear Neil Stanley, I was wondering if you knew who is in "charge" of the Kalorama Park Project,
and where I might find a detailed work schedule with time goals. I'd also like to get a complete
list of contractors and subcontractors and the amount they were supposed to be paid and the actual
amount that they will be paid. This information will be shared with the neighborhood surrounding
the park so they can get a better appreciation of the progress, quality and the cost of work
performed on their behalf.
> Thanks in advance. Eddie Becker
>
> Cc Jim Graham
------------------------------------------------------------------------------------
--- "Stanley, Jackie (DPR)" <Jackie.Stanley at dc.gov> wrote:
> From: "Stanley, Jackie (DPR)" <Jackie.Stanley at dc.gov>
> To: "'eddie_becker at yahoo.com'" <eddie_becker at yahoo.com>
> Subject: Kalorama Park Project
> Date: Mon, 22 Nov 2004 11:28:08 -0500
>
> Good Morning Mr. Becker,
>
> The purpose of this e-mail is to acknowledge your request for specific
> information related to the Kalorama Park Project.
>
> Based on the information you're requesting it may take a few days to collect
> the data and respond accordingly.
> Therefore, I will provide you with a response by the cob on Wednesday at the
> earliest and Friday at the latest.
>
> Thank you,
>
> Jackie Stanley
> Capital Projects Specialist
> 202-541-6458
-------------------------------------------------------
> Date: Fri, 19 Nov 2004 09:02:29 -0500
> From: "Jim Graham" <jim at grahamwone.com>
> Subject: Re: UPDATE ON KALORAMA PARK
> Thanks, I am glad the center will be open. Please move rapidly on the
> balance. I am passing this along. Bests CM Jim Graham
>
> I typically answer emails before 9 AM on weekdays. If you email me after
> that, it is likely that you will hear from me the next weekday. If there
> is a need to communicate prior to that, you may wish to call me.
>
> Jim Graham, Councilmember, Ward One, 1350 Pa. Ave., NW, #406,
> Washington, DC 20004. 202-724-8181; 202-724-8109 (fax).
> ---------------------------------------------------------
> -----Original Message-----
> From: Stanley, Neil (DPR) [mailto:Neil.Stanley at dc.gov]
> Sent: Thursday, November 18, 2004 10:41 PM
> To: 'Jim Graham'
> Cc: 'Lisa Franklin-Kelly'; Becher, Drew (DPR); Loza, Teddy (COUNCIL)
> Subject: Re: UPDATE ON WALTER PIERCE AND KALORAMA PARKS
> Our contractors have been asked to re-direct the safety fence while we
> work to complete the paving work. If all goes well, the public will have
> access to the recreation center (but not the playground) on Monday. I'll
> update you again once I have additional information.